Complete reconstruction of the airport in Noviy Urengoy will take 3.5 years
10:08 14 марта 2018
Категории: News in English

2.5 years are given for reconstruction of the airport in Noviy Urengoy, 3 years – for the terminal. Fulfillment of the project will be completed with development of the terminal apron. Building work will be started within the new building season. Selection of the general contractor and preparatory work will be started already this year. This information was given on the 14th of March by the director general of “Airports of Regions” Yevgeniy Chudnovskiy to journalists.
He underlines unique character of the project. This is the first concession that allows the region to solve own problems and to shift necessary development of both the terminal complex and the aerodrome infrastructure to the investor’s shoulders. “The scheme is new. We are pioneers of the process”, as he notes.
As the governor of Yamal-Nenets Autonomous Okrug Dmitry Kobylkin notes, the airport in Noviy Urengoy is the largest air harbor of Yamal, it should be modern, comfortable and safe. The head of the region thanked all the participants of the project. He is sure that the airport will not be the only one object being reconstructed within the concession.
As we should remind, the concession agreement for designing, building, reconstructing and operating of the airport complex in Noviy Urengoy was signed between the government of Yamal-Nenets Autonomous Okrug and the company “UrengoyAeroInvest”.